            is located on Bhuj - Anjar State Highway, 12 Kms away from Bhuj, appx. 
            1 Km interior. The village has 43 families. All of them belong to 
            economically hard-pressed tenants. When houses were they lived got 
            totally destroyed, on 26th Jan 2001 due to the earthquake, they had 
            no place to live.
Kukma 
            is located on Bhuj - Anjar State Highway, 12 Kms away from Bhuj, appx. 
            1 Km interior. The village has 43 families. All of them belong to 
            economically hard-pressed tenants. When houses were they lived got 
            totally destroyed, on 26th Jan 2001 due to the earthquake, they had 
            no place to live. 
            
               
          The Residents: 
          
          The village consists of Brahmin community.
          
          Association with BAPS
          Sadhus from Bhuj BAPS 
          temple visited this village on 28-01-2001, with relief materials, which 
          was their first association with the villagers. Subsequently, BAPS adopted 
          this village for rehabilitation. Allocation of land and governmental 
          procedures took more than a year. As soon as the new plot of land was 
          acquired, one Km away form the ruins, Bhumipujan was performed on 29.04.2002. 
          With the blessings of HDH Pramukh Swami Maharaj the new colony Pramukh 
          Swami Nagar, was born. Actual construction work started in May 1st 2002. 
          Pramukh Swami 
            Nagar:-
             The 
            site is spread in (5,600 Sq. m.) land area, with same type of houses 
            for all beneficiaries.
The 
            site is spread in (5,600 Sq. m.) land area, with same type of houses 
            for all beneficiaries. 
          
            
            
            
            
            Fact sheet - Timeline 
            Foundation Stone Ceremony - 29 April 2002.
            Actual Work Started - 1st May 2002. 
            Allocation of land and governmental procedures took almost one year. 
            As soon as the site for the new colony was allotted, Bhumipujan was 
            performed on 29 April 2002 and work started after one day.
            Date of Completion - 1st 
            week of November 2002 
              
            Houses: 
            43 Houses
            
          
             
              | Type | A | 
             
              | Plot | 100 Sq. mt. | 
             
              | Built up | 46 Sq. mt. | 
             
              | Actual | 40.00 Sq. mt. | 
             
              | Front | 7.20 Sq. mt. | 
             
              | Sides | 9.20 m. & 6.0 m | 
             
              | Accommodation | Two Room, Kitchen, Toilet Veranda | 
             
              | Total Houses | 43 | 
          
          Infrastructure:
            Water, electric power and sewage system is provided by BAPS.
          